UPDATE Mon Oct. 3: It appears that TransLink has reversed the drop in service frequencies on the Expo Line as part of the upcoming changes. While retaining the lengthening of Mark I trains to 6 cars, Expo Line passengers will continue to have 6-minute service on each branch during off-peak periods, and peak period service will be increased versus the original proposal. The issues brought up in this blog post were cited by TransLink as having contributed to the decision to reverse the frequency changes.

The following reports have further confirmed the changes:


Original text below:

Yes, you read that headline correctly – this is not a joke, and not some mis-interpretation of the upcoming SkyTrain changes on October 22nd. TransLink is going to reduce Expo Line service frequencies, at all times of day, on October 22nd.

skytrain-oct-22
The SkyTrain as it will operate after October 22nd. The Expo Line is shown in blue.

The Expo Line, the original SkyTrain corridor extending to King George Station in Surrey, is the busiest line on our SkyTrain rapid transit system. After poking around on TransLink’s website along with forumers on discussion boards, I made a startling discovery about the upcoming October 22 SkyTrain changes. It appears that, for no apparent reason, TransLink is sneaking a reduction in service frequencies at all times of day on the Expo Line, and this is not being communicated with the public.

I initially confirmed this when I and some fellow online forumers on SkyscraperPage, CPTDB and others were looking into SkyTrain’s schedule changes. The operating schedules for SkyTrain, SeaBus and West Coast Express can be accessed through TransLink’s “bus schedules” page by typing in corresponding numbers in the 900s. The current Expo and Millennium Lines were using numbers 999 and 996, but we discovered that the numbers 992 and 991 were being utilized for a brand new schedule effective starting in October.

This schedule showed that SkyTrain frequencies were clearly being subject to a decrease at basically all times of day – not just the peak service hours. Mid-day and evening service (currently at every 6 minutes) and weekday day-time service (currently at every 7 minutes) would be operated less frequently at every 7.5 minutes. Some parts of the schedule have seen a minor service increase from 10 to 8 minutes, but this is happening at parts of the day where the issue of frequency is not as critical – such as late at night on weekdays and weekends.

skytrain-decrease
Wait times at Surrey SkyTrain stations will be 7-8 minutes after October 22nd, compared to the current 6 minutes, during mid-day periods.

TransLink representatives at a recent media event had commented that passengers would be waiting an “extra 10 seconds at peak times” (see: report by Jeff Nagel on Surrey Leader), although trains would be consolidated into longer consists (i.e. 6-car Mark I, 4-car Mark II or Mark III) make up for this and ensure a high capacity.

However, the actual schedule change I have uncovered shows that the actual increase in wait time is closer to 25 seconds on the Expo main-line inbound from Columbia Station (108 -> 133 seconds), and will be as high as 38 seconds on average on the King George branch in Surrey (162 -> 200 seconds). In addition, in a move that has by far been completely unannounced, passengers will be waiting up to an additional 1.5 minutes on each branch during mid-days and other off-peak periods.

TransLink has never confirmed this explicitly during Q&A sessions for the October 22 changes, but has recently quietly confirmed the change on its SkyTrain schedules page, which are now showing a “Current” and “Oct. 22” schedule that reflects the proposed change on the “bus schedules” page. For more info, see the page:

TransLink > SkyTrain Schedules > Expo Line

Frequencies will change as follows, according to TransLink’s website:

Expo Line – Waterfront to King George
Time of Day Frequency before Oct 22nd Frequency after Oct 22nd
Peak Hours (6-9AM, 3-6PM) 2-4 min. 2-5 min.
Mid-day (9AM-3PM) 6 min. 7-8 min.
Evening (6PM onwards) 6 min. 7-8 min.
Late night 8-10 min. 8 min.
Early Sat/Sun 8-10 min. 8 min.
Sat, Sun/Holidays 7-10 min. 7-8 min.

The changes in service frequencies will mean longer waits for trains at almost all times of day, making the Expo Line less reliable and less versatile to its many riders. It will also result in more overcrowded SkyTrain platforms – as longer waits between trains means each platform will need to service up to 25% more waiting passengers than there are today with higher frequencies. Some of our stations – particularly ones in the middle of reconstruction, such as Metrotown Station – could have trouble having to accommodate for additional waiting passengers.

Today's higher frequencies prevent platform overcrowding because the train arrives sooner to allow passengers to be on their way. The service changes will mean more overcrowded SkyTrain platforms.
Today’s higher frequencies help prevent platform overcrowding because the train arrives sooner to allow passengers to be on their way. The service changes will mean more overcrowded SkyTrain platforms on the Expo Line, as platforms will have to handle as much as 25% more waiting passengers.

While train lengths are increasing, I do see the possibility that overall service capacities will come down as a result of the changes. Going from 6 to 7.5 minute service in the mid-day and on weekends is a substantial 20% reduction in service frequency, and while Mark I trains would be operated in longer 6-car formation, the Mark II trains currently operating in 4-car formation would be essentially the same as they are today.

SkyTrain passengers already swallowed a change in 2013 that saw weekend frequencies on the Expo Line drop from 6 to 7 minutes on each branch, as part of a package of cost reductions implemented throughout the entire system to improve cost-efficiency. This has resulted in substantially increased weekend overcrowding, with Saturday PM volumes between Commercial-Broadway and Main Street-Science World stations now nearly at the line’s practical capacity in both directions (see: 2015 Transit Service Performance Review, Appendix E).

Why this makes absolutely no sense, whatsoever.

mark-ii-broadway
Prior to an expansion order in 2009, Mark II trains in 2-car formation were operated alongside Mark I trains on the Expo Line. SkyTrain had the flexibility to offer higher frequencies with the smaller trains, as opposed to lower frequencies with all of the Mark II trains in a 4-car formation.

One of the big advantages to the driver-less, automatic train control technology we use on our SkyTrain system has always been our ability to maintain high frequencies at any time of day, without high operating costs. On our system, shorter trains at higher frequencies can provide the same capacities as longer trains and lower frequencies typically found on other light and heavy rail systems, but without the higher costs associated with needing extra drivers and conductors.

This has made us a continental leader in providing rail rapid transit services among North American cities. I have previously noted that Metro Vancouver is unmatched in its off-peak rail transit service frequencies, when compared to metro areas of similar sizes – in which off-peak service on the rail network is generally provided every 10 to 15 minutes on individual lines.

SEE EXAMPLE
Portland, Denver, Pittsburgh and Cleveland are other metro areas similar in size to Metro Vancouver with rail transit systems, yet none of them are able to provide the kinds of service frequencies we have on our fully-automated SkyTrain system. Go [HERE] to see a comparison of our service frequencies against these cities’.

What can be done about this

TransLink is dealing with a public credibility problem and this is certainly not going to help their case. The entire service change on October 22nd is being made without a formal public consultation process, which wouldn’t really be so much of a problem if there weren’t going to be major changes in service frequencies on existing lines – but there are. And, there has been no indicated rationale as to why mid-day and weekend service frequencies are also being reduced.

I don’t see any barriers to continuing to provide a 6-minute service off-peak with the longer trains, or utilizing the existing schedule whereby peak service is operated at higher frequencies, with a mix of trains including shorter 4-car Mark I trains.

UPDATE Fri Sept. 23 @ 10:24AM: At the moment, the fabrics of how this decision went through are still unknown to me. However, I am now working on communicating with BCRTC and TransLink’s planning department to get some answers and gauge whether I could push to have this decision reversed.
UPDATE Mon Oct. 3: It appears that TransLink has reversed the drop in service frequencies on the Expo Line as part of the upcoming changes. While retaining the lengthening of Mark I trains to 6 cars, Expo Line passengers will continue to have 6-minute service on each branch during off-peak periods, and peak period service will be increased versus the original proposal. The issues brought up in this blog post were cited by TransLink as having contributed to the decision to reverse the frequency changes.

The following reports have further confirmed the changes:

22, KPU Geography, J-POP enthusiast. Founding director of SkyTrain for Surrey.

New SkyTrain changes hide drop in service (UPDATE: TransLink to reverse service drop)

7 thoughts on “New SkyTrain changes hide drop in service (UPDATE: TransLink to reverse service drop)

  • September 22, 2016 at 2:13 pm
    Permalink

    Is this disguise of degraded frequency on the SkyTrain Expo line being implemented to try and make the absurd Surrey LRT vision more palatable? There is no doubt that LRT if it ever comes to fruition in Surrey(hopefully NOT), the frequency would never match the current SkyTrain standards.

    Reply
    • September 22, 2016 at 2:50 pm
      Permalink

      There’s no reason there’d be a connection between this and the Surrey LRT plans, but I do know that rail planning & ops manager Ian Fisher has quite a liking for LRT and the Surrey proposal…

      Reply
    • September 22, 2016 at 10:46 pm
      Permalink

      There doesn’t seem to be any reason why this and that should be linked, but I do know that rail planning head Ian Fisher seems to have quite a thing for LRT and Surrey’s proposal.

      Reply
  • October 3, 2016 at 8:21 am
    Permalink

    The reason why translink is cutting service on the expo line is because they do not have enough trains to provide high frequency service on both the Mline and Expo line after the evergreen extension opens. As well service on the Mline is going to be the same after October 22 not higher. Trains running twice as often but half the size (2 car mark IIs instead of 4 car mark IIs) equals the same service. We deserve a better transit authority that stops lying to the public and wastes public money. The provincial government needs to start supporting transit expansion not freeway expansion for the growing region.

    Reply
    • October 3, 2016 at 3:46 pm
      Permalink

      Hey cj. Did just want to get back to you in case you didn’t notice the post update but TransLink has reversed the frequency cuts (as in there will not be a drop in service frequencies) so a train shortage is definitely not the issue. It shouldn’t have been an issue as the Mark I trains, which operate in a mix of 4 and 6-car consists, would be changed to run entirely with 6 cars – so I was wondering why not run with the existing mix & setup.

      I have no complaints about the Millennium Line changes; this would have followed the earlier convention of using our ATC tech to offer higher frequencies with shorter trains, which would have been a very good thing but I was concerned the reverse was going to be applied on the Expo Line, the busiest transit route in our system.

      Reply
  • October 6, 2016 at 12:30 pm
    Permalink

    While Translink has said they will reverse the decision, the frequencies have not been updated on the website – still showing the lower frequencies.
    I have no issue with running shorter trains at double the frequency on the M Line – that is the point of the automatic train technology. This best matches capacity to demand but provides a high frequency service.

    Reply
  • October 12, 2016 at 4:08 pm
    Permalink

    Surrey LRT is being driven by a romantic notion that trains running along the street at a lower speed somehow make it a livable pedestrian oriented city centre. There is something nice and relaxing about the image, but it’s crap when it comes to moving people. People only want two things from rapid transit – fast and frequent. The surrey LRT might work as a people mover around the downtown, but it will not add much to moving people around the region.